Decision of the European Ombudsman closing his inquiry into complaint 2220/2010/(MB)ELB against the European Commission
Päätös
Kanteluasia 2220/2010/ELB - Tutkittavaksi otetut kantelut, pvm Maanantaina | 21 helmikuuta 2011 - Päätökset, pvm Keskiviikkona | 14 joulukuuta 2011 - Toimielin, jota kantelu koskee Euroopan komissio ( Ei hallinnollista epäkohtaa )
The background to the complaint
1. The complaint concerns the execution of a contract signed between the complainant and the "Union économique et monétaire Ouest Africaine" ('UEMOA')[1] in the framework of the Regional Integration Support Programme. The complainant carried out a study for UEMOA and did not receive his full fees. He argued that as the European Commission "co-signed" the contract, it should pay him. The Commission refused to do so.
2. The complainant therefore turned to the European Ombudsman.
The subject matter of the inquiry
3. The complainant alleged that:
- the Commission failed to ensure that UEMOA complies with its contractual obligations towards the complainant, in particular the obligation for UEMOA to pay the complainant's fees.
- the Commission failed to assist the complainant in seeking an amicable settlement with UEMOA.
4. The complainant claimed that:
- the Commission should ensure that UEMOA complies with its contractual obligations and pays the complainant's fees.
- the Commission should assist the complainant in seeking an amicable settlement with UEMOA.
The inquiry
5. On 12 and 23 October 2010, 19 and 28 November 2010 and 17 and 21 January 2011, the complainant submitted a complaint and supporting documents to the Ombudsman. On 21 February 2011, the Ombudsman opened an inquiry and forwarded the complaint to the Commission, which sent its opinion to the Ombudsman on 13 July 2011. The opinion was forwarded to the complainant, who then submitted his observations on 4 and 5 August 2011.
The Ombudsman's analysis and conclusions
Preliminary remark
6. In his observations, the complainant remarked that the Commission's opinion is neither signed nor dated. The Ombudsman would like to clarify that the Commission's opinion was signed by Commissioner Piebalgs and is dated 13 July 2011.
A. Alleged failures to ensure that UEMOA complies with its contractual obligations and to assist the complainant in seeking an amicable settlement with UEMOA and related claims
Arguments presented to the Ombudsman
7. The complainant explained that he signed a contract with UEMOA in September 2005 by virtue of which he was engaged to carry out a study. The Commission's Delegation in Burkina-Faso "co-signed" the contract and funded it. At the end of the study in December 2005, the complainant submitted a report on the work carried out. On 31 March 2006, UEMOA informed the complainant that it was not entirely satisfied with the report. The complainant was paid for his work in part: he received EUR 42 000. In his view, the amount of EUR 102 539 is outstanding. The complainant argued that UEMOA failed to challenge the report within the 30-day deadline. Therefore, the report should have been accepted and the complainant should have been paid in full.
8. In view of the difficulties which he encountered in obtaining payment from UEMOA, the complainant requested the help of the Commission's Delegation. In July 2006, the Commission's Delegation contacted UEMOA about the issue. The complainant then requested that arbitration proceedings be initiated[2]. Subsequently, he instituted legal proceedings against UEMOA before the French courts[3]. On 1 April 2010, the Court of Appeal of Montpellier ordered UEMOA to pay the outstanding amount[4], which UEMOA failed to do. The complainant then turned to the Commission's Delegation and asked it to pay him the outstanding amount. He argued that the Commission drafted the General and Special Conditions applicable to the contract and made a first advance payment.
9. In its opinion to the Ombudsman, the Commission explained that, in February 2000, it signed a financing agreement with UEMOA with a view to contributing to the Regional Integration Support Programme. It is in the framework of this programme that the contract between the complainant and UEMOA was signed. The financing of the contract amounted to EUR 210 035 and the contract duration was of three months.
10. The Commission explained that in the framework of the decentralised management of EU external actions, the contractor has a legal relationship solely with the contracting authority (in this case, UEMOA) which is responsible for the tender. The Commission acts as a financing body and its obligations towards the contracting authority are governed by the ACP-EC Partnership Agreement and the financing agreement. These texts do not allow the Commission to substitute itself for UEMOA. In the execution of contracts financed by the European Development Fund ('EDF'), the interventions of the Commission's representatives are limited to checking whether the financing conditions are met[5]. The Commission can only check that procedural rules have been complied with.
11. In accordance with its obligations, the Commission checked that the procedure had been complied with and that it was informed of potential breaches of procedure[6]. Hence, the Commission immediately contacted UEMOA when it was informed of late payments by the complainant. The Commission understood that the conflict between the complainant and UEMOA concerned the execution of the contract. Each party took the view that the other party had incurred delays and UEMOA considered that the complainant delivered a poor service. It put forward the complainant's non-compliance with several contractual provisions and the fact that he did not fully execute the contract.
12. The Commission underlined that the complainant admitted that he did not carry out the required tasks in the transport field. He thus decided to reduce the invoice by 25%. As regards the other areas which UEMOA considered not to have been carried out fully, the complainant explained the difficulties which he encountered and the unilateral changes in the terms of reference. The Commission noted that no modification was made unilaterally by UEMOA. The complainant agreed to the reduction in the duration of the contract and in the amount due to him under the contract.
13. At a later stage, the complainant also invoked the changes in the methods used in the study in order to explain why the terms of reference might not have been fully complied with. According to the Commission, the aim of these changes in the methods was to clarify the tasks to be carried out by the complainant. However, no tasks were eliminated.
14. In light of the above, the Commission considered that it could not be excluded that UEMOA's arguments were at least partially well-founded. The Commission concluded that it had correctly ensured that the rules and procedures applicable to external actions financed by the EDF were complied with.
15. As regards the arbitration proceedings, the Commission pointed out that Article XLV.2 of the contract concerns the settlement of disputes between the parties. The parties should first try to find an amicable settlement to the dispute. If no amicable settlement can be found, then the dispute should be settled in accordance with Article 45(5) of the General Conditions of Service Contracts financed by the EDF. According to that article, disputes should be settled through arbitration, which may be preceded by conciliation.
16. The Commission further explained that it immediately offered to act as conciliator. It indicated to UEMOA the way forward. The complainant never expressed his wish that the Commission assume such a role. In order for the conciliation procedure to be initiated, both parties must agree to it. In addition, he had not contacted the Commission for 21 months, and only did so in order to inform it of the order of the President of the Bar ruling that UEMOA should pay the complainant. The Commission noted that, by initiating legal proceedings, the complainant did not comply with the provisions on dispute settlement provided for in the contract. The complainant had no obligation to agree to the conciliation procedure. However, he should have used the arbitration procedure.
17. Following the submission of the present complaint, the Commission met UEMOA, which indicated that it maintained its position as regards the poor quality of the work carried out by the complainant but that it was ready to settle the dispute financially or, alternatively, to initiate arbitration proceedings.
18. In his observations, the complainant argued that the Commission incorrectly reported certain facts relating to the duration of the contract, the date on which it was signed, its scope and the delivery of the preliminary and final reports. He referred to the difficult circumstances in which the contract was carried out. He disagreed with the Commission's comments about the quality of the report. According to him, reducing the duration of the contract would ruin the project. The complainant also referred to the lack of co-operation from UEMOA.
19. He pointed out a new fact, namely the order of the French Court of Cassation of 16 June 2011, which was forwarded to the Commission.
20. The complainant's main argument is that UEMOA remained silent for three months following the delivery of the final report. According to the applicable rules, if no reply is received within 30 days, the report is approved and the outstanding amounts should be paid. The Commission should not have accepted that payment be withheld. Secondly, UEMOA failed to comply with the French courts' rulings.
21. The complainant stated that he failed to understand the Commission's reference to the desire of UEMOA either to settle the dispute financially or to initiate arbitration proceedings. He stated that two courts had already ruled on the matter in his favour.
The Ombudsman's assessment
22. The present inquiry concerns the alleged failure of the Commission to help resolve the conflict between UEMOA and the complainant. The Ombudsman will thus limit the present inquiry to determining whether the Commission took all reasonable steps to help resolve the dispute between the said parties.
23. The Ombudsman takes the view that if the Commission is informed of a problem between a contractor and a beneficiary, good administrative practice requires it to seek to verify the relevant facts at the outset. If the Commission were then to find that the position of the contractor, or the position of the beneficiary, is manifestly well-founded, it should inform the parties of its views in order to assist them in resolving the matter. If the facts are unclear, the Commission should also take reasonable steps to resolve the matter (for instance, through conciliation).
24. In the present case, when the Commission was contacted by the complainant about UEMOA's alleged late payments, it immediately contacted UEMOA. The Commission noted that each party took the view that the other party had incurred delays and UEMOA considered that the complainant delivered a poor service (UEMOA put forward the complainant's non-compliance with several contractual provisions and the fact that he did not fully execute the contract). In light of the above, the Commission thus considered that it could not be excluded that UEMOA's arguments were at least partially well-founded.
25. The Ombudsman also notes that the Commission further explained that it immediately offered to act as conciliator and indicated the way forward to UEMOA. The Ombudsman notes that, on 19 March 2007, the Commission suggested that the complainant and UEMOA assess the work carried out in order to determine the amount which was still due to the complainant. On 20 July 2007, the Commission accepted to act as conciliator.
26. On 7 August 2007, UEMOA made a proposal to settle the dispute, offering to pay the complainant CFA 14 076 464[7]. This proposal was rejected by the complainant, who made a counter-proposal on 22 February 2008. On 19 December 2008, UEMOA suggested that the parties adopt a common method to assess the work carried out by the complainant. In the meantime, the complainant chose to refer the matter to the French courts.
27. The Ombudsman takes the view that the Commission did try to solve the matter between the complainant and UEMOA. He notes that, in his observations, the complainant seems to admit that the Commission did its duty when it recommended to UEMOA that it seek an amicable settlement to the dispute.
28. The Ombudsman also notes that the Commission met UEMOA after the submission of the present complaint in order to assess the situation. UEMOA indicated that it maintained its position as regards the poor quality of the work carried out by the complainant, but that it was ready to settle the dispute financially or otherwise to initiate arbitration proceedings.
29. The Ombudsman thus considers that the Commission took reasonable steps to investigate the matter and that the position it took was reasonable, given the information in its possession. The Ombudsman again underlines that the Commission's role is limited to taking reasonable steps to help resolve the dispute between the complainant and UEMOA. The position taken by the Commission does not purport to establish the contractual position of the complainant or of UEMOA in a definitive manner. The Ombudsman notes that if the complainant continued to disagree with UEMOA on the issue of compliance by both parties with their respective contractual obligations, such an issue could only be definitively decided upon by an arbitral tribunal or by a competent court.
30. In light of the above, the Ombudsman concludes that there has been no maladministration by the Commission and that the claims cannot be sustained.
B. Conclusions
On the basis of his inquiry into this complaint, the Ombudsman closes it with the following conclusion:
There has been no maladministration by the Commission.
The complainant and the Commission will be informed of this decision.
P. Nikiforos Diamandouros
Done in Strasbourg on 14 December 2011
[1] The contract is entitled "Contrat de services pour la réalisation d'enquêtes sur les pratiques anticoncurrentielles (8 ACP ROC 021)".
[2] Letter from ICABE to UEMOA dated 17 January 2008 and letter from ICABE to the Commission's Delegation of 26 February 2008.
[3] Order of the President of the Bar of 10 April 2009 ruling that UEMOA should pay the complainant, confirmed by a judgment of the Court of Appeal of Montpellier of 1 April 2010.
Order of removal from the register of the Court of Cassation of 9 December 2010 and order of disqualification of the Court of Cassation of 16 June 2011.
[4] The French Court of Cassation confirmed the ruling of the Court of Appeal against UEMOA. However, the complainant has still not been paid by UEMOA.
[5] Case 126/83 STS v Commission [1984] ECR 2769, paragraph 16; Case 118/83 CMC and others v Commission [1985] ECR 2325, paragraph 28 and Case 33/82 Murri Frères v Commission, [1985] ECR 2759.
[6] Article 36(j) of Annex IV to the Partnership agreement between the members of the African, Caribbean and Pacific Group of States of the one part, and the European Community and its Member States, of the other part, signed in Cotonou on 23 June 2000, OJ 2000 L 317, p. 3 ('the Cotonou Agreement').
[7] This amount was equivalent to EUR 21 459 in September 2011.