Decision on how the European Commission dealt with a request for public access to documents concerning EU funding granted to support United Nations Special Rapporteurs (case 1203/2022/NH)

The case concerned how the European Commission dealt with a request for public access to documents concerning EU funding granted to support three United Nations Special Rapporteurs.

The complainant initially took issue with the delay by the Commission in dealing with the request. Following the decision by the Commission to confirm its initial refusal to grant access to certain documents, the complainant also questioned whether the Commission was justified in withholding access.

The Ombudsman found that the considerable delay by the Commission in dealing with the request constituted maladministration, and restated the recommendation and suggestions she made following a recent inquiry concerning delays by the Commission in dealing with requests for public access to documents.

The Ombudsman found that the Commission was justified in withholding access to certain documents but that it could have granted wider access to parts of four interim financial reports. The Ombudsman encourages the Commission to provide the complainant with the widest possible access to these reports, and will make a suggestion to that effect.

Background to the complaint

1. Between 2016 and 2021, the Office of the United Nations High Commissioner for Human Rights (hereafter ‘OHCHR’) received financial support from the EU budget to support UN Special Rapporteurs on human rights defenders, freedom of association, and freedom of expression. The European Commission provided the funding by means of a direct grant under the European Instrument for Democracy and Human Rights (EIDHR) programme.

2. In December 2021, the complainant, a non-governmental organisation based in France, made a request for public access to documents[1] held by the Commission concerning the grant, namely:

· the annual progress and financial reports mentioned in the Commission’s reply to a parliamentary question[2] concerning the grants;

· the contract between the Commission and the beneficiaries of the EU funding.

3. In February 2022, the Commission replied, stating that it had identified twelve documents falling within the scope of the request: the grant contract, including seven annexes, and four interim narrative and financial reports for the years 2016, 2017, 2018 and 2019. It granted full access to three annexes, and access to parts of the grant contract. It refused to disclose the remaining documents because the originator of the documents, the OHCHR, objected to their disclosure. In doing so, the Commission invoked exceptions provided for under the EU legislation on public access to documents (Regulation 1049/2001), arguing that disclosure would undermine the protection of the public interest as regards the EU’s international relations and the protection of privacy and the integrity of the individual.[3]

4. The complainant asked the Commission to review its decision to refuse access to the remaining documents (by making a ‘confirmatory application’).

5. Having received no reply despite several reminders, the complainant turned to the Ombudsman in June 2022.

The inquiry

6. The Ombudsman opened an inquiry into the Commission’s failure to reply to the confirmatory application submitted by the complainant.

7. In the course of the inquiry, and in view of the persisting delays, the Ombudsman inquiry team inspected the documents at issue. It also inspected the file related to the consultations of third parties carried out by the Commission.

8. The Commission eventually replied to the confirmatory application. However, since the complainant remained dissatisfied with the level of access granted, the Ombudsman continued the inquiry into the Commission’s decision to refuse access to seven documents in their entirety.

The failure to reply to the confirmatory application within the applicable deadlines

The Ombudsman's assessment

9. According to Regulation 1049/2001[4], an EU institution should, within 15 working days from registration of the confirmatory application, either grant access to the document requested or, in a written reply, state the reasons for the total or partial refusal. The time limit of 15 working days may be extended by a further 15 working days in exceptional circumstances.

10. In this case, the Commission took over one year to take a decision on the complainant’s confirmatory application. This egregious delay constitutes maladministration.

11. The inspection by the Ombudsman inquiry team of the Commission’s file concerning the third party consultations it carried out showed that the third party in this case - the OHCHR - was consulted three times between March and December 2022. Having reviewed the exchanges, it is not clear to the Ombudsman why so many consultations were necessary.

12. The Ombudsman has consistently taken the view that ‘access delayed is access denied’. In a recent finding of maladministration concerning the systemic delays by the Commission in handling requests for public access to documents[5], the Ombudsman set out a recommendation and several suggestions for improvement that address the concerns outlined above. As such, the Ombudsman will not repeat those elements in this decision.

The decision to refuse access to certain documents

Arguments presented to the Ombudsman

13. In its confirmatory decision, the Commission redefined the scope of the complainant’s request concerning 18 documents, of which it had already granted partial access to four, namely the grant contract and three annexes.[6] It granted wider access to seven of the 18 documents. The Commission redacted parts of those documents based on two exceptions set out in Regulation 1049/2001, which relate to the protection of the public interest as regards international relations and the protection of personal data.[7]

14. The Commission refused to disclose the remaining seven documents, invoking two exceptions under Regulation 1049/2001 related to the protection of commercial interests and personal data.[8]

15. It explained that it had consulted the third party from which the documents originate (the OHCHR), which had objected to the disclosure of all documents. The OHCHR argued that it had provided these documents to the Commission on the understanding that they would not be shared further. If the Commission insisted on disclosing the documents, the OHCHR urged the Commission to redact certain parts to protect the relationship of trust.

16. The Commission explained that the requested documents were drawn up in the context of the project ‘Supporting key international actors UN Special Rapporteurs on human rights defenders, freedom of association, and freedom of expression’, which received EUR 1.6 million under the EIDHR programme. The Commission redacted some parts of the documents in order to protect its relationship with the OHCHR, as it will continue to cooperate with the OHCHR in a number of human rights-related projects. Some parts were redacted in order to protect the relations of the OHCHR with other countries, as the redacted parts contain views on the specific situation in some countries in which the UN Special Rapporteurs conducted their activities.

17. The Commission contended that most documents contained personal data, such as names, functions, contact details and handwritten signatures. As such, disclosure would undermine the protection of privacy and the integrity of these individuals,[9] in accordance with EU legislation regarding the protection of personal data[10]. The Commission explained that the legislation on data protection sets out that personal data may only be transmitted to a recipient if they establish that it is necessary to have the data transmitted for a specific purpose in the public interest. It argued that the complainant had not put forward any convincing argument to establish such necessity.

18. Finally, the Commission argued that some documents contained elements that may seriously undermine the commercial interests of the OHCHR. The documents relate to a grant awarded by the Commission under a direct grant procedure, for which the OHCHR had to apply. All documents that involve the application to the grant contain commercially sensitive information, because, the Commission said, they describe in detail the proposed actions to be conducted through the grant, as well as methodologies, internal organisation, particular know-how, strategy and other specific information with competitive value. The Commission contended that public disclosure of such information would undermine the OHCHR’s commercial interests, as it would give other potential grant applicants in future similar calls the possibility to copy from these applications and use it to support their own applications.

19. In particular, the Commission explained that the initial budget proposal, as well as the four interim financial reports for the years 2016-2019, constitute commercially sensitive information as they contain the detailed cost structure and budget estimations of the project. Public disclosure of these documents would also undermine the commercial interests of the OHCHR.

20. In his complaint, the complainant argued that the mandate of the UN Special Rapporteurs, who received EU funding, sets out that they must act in full independence and be free from any outside influence. As such, he believed that the Commission should disclose the requested documents in order for the public to assess whether the obligations of independence were respected in this case. After having received the confirmatory decision, the complainant noted that the wider partial access granted was a positive step, but insisted that he still disagreed with the Commission’s use of the ‘commercial interests’ and ‘privacy’ exceptions to refuse disclosure of seven of the documents, in particular the four interim financial reports.

The Ombudsman's assessment

21. In refusing access to seven documents in their entirety, the Commission relied on the need to protect personal data and the commercial interests of the third party.

22. The inspection of the seven documents confirmed that they contain, in parts, personal data. The Commission correctly argued that, in order to transmit personal data to an applicant, the Commission must first check whether the applicant has demonstrated a need to have this personal data transferred to them for a specific purpose in the public interest. As the complainant in this case did not put forward any need in its confirmatory application, the Commission’s refusal to grant access to the personal data contained in the seven documents was reasonable.

23. As regards the protection of commercial interests, the Commission referred in its confirmatory decision to a general presumption of confidentiality applicable to bids submitted by tenderers under direct management of the EU budget.[11] It considered that “[t]he present case concerns a grant awarded by the Commission under a direct grant procedure to the project EIDHR/2016/379-668 presented by OHCHR” and then assessed the seven documents individually.

24. The first document (document 1.1), entitled “Description of the Action and Logical Framework”, is part of the grant application by the OHCHR. It describes the mandates of the three UN Special Rapporteurs, the proposed methodology of the project as well as the duration and indicative action plan for implementing the project. The Commission refused to disclose the document, arguing that it contained commercially sensitive information on the OHCHR methodology and internal know-how that needed to be protected.

25. EU case-law has recognised that the clauses specific to a project, as well as the methodology and expertise put forward by the project promoter, relate to its specific know-how and contribute to the singularity and attractiveness of the application in the context of calls for proposals. Such information is confidential in nature, having regard, in particular, to the competitive context in which it belongs.[12] As such, it was reasonable for the Commission to consider that the document’s disclosure would undermine the commercial interests of the OHCHR.

26. In the confirmatory decision, the Commission acknowledged that the grant at issue was awarded under the so-called ‘direct grant procedure’, meaning without the publication of a call for proposals. However, the Commission argued that the procedure is still competitive in nature, because, should the document be disclosed, other eligible beneficiaries could copy its elements without investing the same resources that the OHCHR invested when developing the proposal. The Ombudsman finds that argument reasonable.

27. The second document (document 1.3), entitled “Revised budget initialled”, is the OHCHR proposal for an estimated budget for the project when it applied for the grant. It contains the estimated eligible costs and contributions for the project, broken down by budget category. The Commission argued that the information in the document constitutes commercially sensitive information as it contains the detailed cost structure and budget estimations of the project. It considered that public disclosure of these documents would also undermine the commercial interests of the OHCHR, as it would give other potential grant applicants in future similar calls the possibility to copy from the document and use this information to support their own applications.

28. EU case-law has given a wide discretion to EU institutions to refuse disclosure of documents to protect ‘commercial interests’, when the documents contain technical and economic information about an entity awarded a grant, in particular information on costs, proposed prices and the price schedule.[13] In the Ombudsman’s view, it was thus reasonable for the Commission to consider that the OHCHR’s estimated budget for the project was covered by this exception.

29. The third document (document 1.4) is the standard “financial identification form” used by the Commission in its grants and contracts,[14] filled in by the OHCHR. It contains the bank account number of the OHCHR and the name of its treasurer. The Ombudsman takes the view that it was reasonable for the Commission to consider that the ‘commercial interests’ exception applied to this document.

30. The remaining documents (2.1, 3.1, 4.1 and 5.1) are four interim financial reports submitted by the OHCHR for each year of the project. They show a breakdown of the costs of the project, year by year; in other words, they show how the OHCHR actually spent the money.

31. The Commission refused to disclose these documents in their entirety, arguing that they constitute commercially sensitive information given that they contain the detailed cost structure and budget estimations. In view of this, the Commission considered that public disclosure of these documents would undermine the commercial interests of the OHCHR, as it would give other potential grant applicants in future similar calls the possibility to copy from these documents and use this information in support of their own applications.

32. Having reviewed the documents, the Ombudsman acknowledges that the four interim financial reports contain the estimated budget lines of document 1.3 (the revised budget). As such, disclosure of parts of the four reports could indeed reveal some of the information contained in document 1.3.

33. However, the four interim financial reports also detail how the OHCHR used the EU funds received for the project between 2016 and 2019. The Ombudsman is not convinced that the general presumption of confidentiality applicable to bids submitted by tenderers extends to the financial reporting in relation to the awarded grant. As such, it is not clear to the Ombudsman how disclosure of aggregated financial information contained in the four reports - for example, the main budget lines for actual expenditure - is likely to reveal the cost structure of the third party, or would allow potential grant applicants in future similar procedures to copy from these documents in support of their own grant application.  

34. Furthermore, the EU Financial Regulation establishes the principle that there should be transparency in how EU funds are spent: “citizens should know where, and for what purpose, funds are spent by the Union. Such information fosters democratic debate, contributes to the participation of citizens in the Union’s decision-making process, reinforces institutional control and scrutiny over Union expenditure, and contributes to boosting its credibility.”[15] In other words, the public should be adequately informed about the implementation of projects financed using public money.

35. In view of the above, the Ombudsman suggests that the Commission grant partial access to the four interim financial reports, as a minimum access to the information compiled in the confidential annex to this decision.

36. Since the Ombudsman found that the Commission’s refusal to disclose the other documents at issue was reasonable, the Ombudsman finds that no further inquiries are justified. She trusts that, in future, the Commission will grant the widest possible access to financial reports concerning how EU funds are spent by grant beneficiaries, while taking into account the need to protect information that may reveal commercial interests that are not overridden by a public interest in disclosure.

Conclusions

Based on the inquiry, the Ombudsman closes this case with the following conclusions[16]:

The considerable delay by the European Commission in issuing a confirmatory decision in this case constitutes maladministration.

The Commission’s refusal to disclose three of the seven documents at issue (documents 1.1, 1.3 and 1.4) was reasonable.

No further inquiries are justified as regards the refusal by the Commission to disclose the remaining four documents, namely the interim financial reports, but the Ombudsman makes a suggestion as regards those documents below.

The complainant and the Commission will be informed of this decision.

Suggestion for improvement

The Ombudsman suggests that the Commission grant partial access to the four interim financial reports (documents 2.1, 3.1, 4.1 and 5.1), as a minimum access to the information compiled in the confidential annex to her decision.

 

Emily O'Reilly

European Ombudsman

Strasbourg, 25/07/2023

 

 

[1] In line with Regulation 1049/2001 regarding public access to European Parliament, Council and Commission documents: https://eur-lex.europa.eu/legal-content/en/TXT/?uri=CELEX%3A32001R1049.

[2] See written question E-004340/2021, available at: https://www.europarl.europa.eu/doceo/document/E-9-2021-004340-ASW_EN.html

[3] In accordance with Articles 4(1)a third indent and 4(1)b of Regulation 1049/2001.

[4] Article 8 of Regulation 1049/2001.

[5] See the Recommendation on the time the European Commission takes to deal with requests for public access to documents (strategic inquiry OI/2/2022/OAM), available at: https://www.ombudsman.europa.eu/en/recommendation/en/167661

[6] The content of the documents is the same as the 12 documents identified at initial stage, but with a different numbering.

[7] In accordance with Articles 4(1)a third indent and 4(1)b of Regulation 1049/2001.

[8] In accordance with Articles 4(2) first indent and 4(1)b of Regulation 1049/2001.

[9] Article 4(1)(b) of Regulation 1049/2001.

[10] Regulation (EU) 2018/1725 on the protection of natural person with regard to the processing of personal data by the Union institutions, bodies, offices and agencies and on the free movement of such data: https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX%3A32018R1725

[11] With reference to the judgment of the General Court of 29 January 2013, Cosepuri Soc. Coop. pA v European Food Safety Authority (EFSA), T-339/10, EU:T:2013:38, paragraph 101.

[12] See the judgment of the General Court of 21 October 2010 in case T-439/08, Agapiou Joséphidès v Commission and EACEA, paragraph 127, available at: https://curia.europa.eu/juris/liste.jsf?language=en&num=T-439/08

[13] See the judgment of the General Court of 21 September 2016 in case T-363/14, Secolux v Commission, paragraphs 53-54, available at: https://curia.europa.eu/juris/liste.jsf?num=T-363/14&language=EN

[14] The template used by the Commission is available here: https://commission.europa.eu/system/files/2019-06/fich_sign_ba_gb_en_0.pdf

[15] Recital 11 of Regulation (EU, Euratom) 2018/1046 of the European Parliament and of the Council of 18 July 2018 on the financial rules applicable to the general budget of the Union, available at: https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=celex%3A32018R1046

[16] This complaint has been dealt with under delegated case handling, in accordance with the Decision of the European Ombudsman adopting Implementing Provisions, available at: https://www.ombudsman.europa.eu/en/legal-basis/implementing-provisions/en.