Decision on the Delegation of the European Union to Papua New Guinea’s decision to reject a tender as abnormally low (case 3171/2025/FA)
Decision
Case 3171/2025/FA - Opened on Thursday | 27 November 2025 - Decision on Wednesday | 07 October 2026 - Institution concerned European Commission ( Maladministration found ) - Country Italy
Complaint submitted
30/10/2025Analysis of the complaint
30/10/2025Inquiry ongoing
27/11/2025Inquiry outcome
07/10/2026
The case concerned the decision of the Delegation of the European Union to Papua New Guinea to reject the complainant’s tender as abnormally low. The complainant argued that the Delegation failed to ask for specific clarifications, to reason its decision and based its rejection on elements unrelated to the price quoted in the tender.
The Ombudsman found that the Delegation should have been more specific when requesting clarifications from the complainant on the price and should have established a clear link between the price and all the elements taken into consideration in its assessment. The Delegation also failed to sufficiently substantiate its decision to reject the tender as abnormally low, in breach of the duty to state reasons. These shortcomings amount to maladministration.
While the Commission provided additional clarifications during the inquiry, the Ombudsman found that these clarifications did not sufficiently address the shortcomings identified.
The Ombudsman considered that it would not be appropriate to make a corresponding recommendation in this case as the contract has been awarded. She nevertheless made three suggestions aimed at preventing such problems occurring in future similar cases.
Background to the complaint
1. The complainant is the leader of a consortium which was selected as a contractor for Lot 6 of the Framework Contract Services for EU’s external action 2023 (FWC SEA 2023). Under this framework contract, the award of specific contracts is carried out by inviting all contractors under the relevant lot to submit a tender for the specific assignment. The contracting authority then evaluates the tenders and awards the specific contract to the contractor offering the best value in accordance with the applicable criteria.
2. In August 2025, the complainant submitted a tender for a specific fee-based contract under lot 6 of FWC SEA 2023 on “Technical Assistance to the Papua New Guinea Department of National Planning and Monitoring on EU Development Cooperation”. The Delegation of the European Union to Papua New Guinea (‘the Delegation’) is the specific contracting authority for this contract.[1]
3. In August 2025, the Delegation contacted the complainant. It asked for clarifications regarding what it saw as a low offer, in terms of price, compared to the market for the services in question. It also asked the complainant to demonstrate compliance with labour and social obligations, to indicate the backstopping services[2] in place and to explain how it would proceed if an expert became unavailable or needed to be replaced.
4. The complainant submitted clarifications the following day. In relation to its financial offer, it explained that it had hired a local expert based in Papua New Guinea, which significantly reduces travel and subsistence expenses, and had secured from him a competitive daily fee. The complainant also confirmed that its offer complied with the applicable legislation and contractual obligations. Regarding backstopping arrangements, it explained that it had a dedicated team in place which would provide continuous technical and administrative support to the expert throughout the assignment. The complainant further clarified that, if the expert became unavailable, it would provide for a replacement from its established pool of experts.
5. In September 2025, the Delegation informed the complainant that it had rejected its tender because it considered it to be abnormally low based on Annex I, point 23 of the Financial Regulation.[3] In particular, it found that “the price proposed is considerably less than that of the normal market price, which may affect the sustainability of the service provision”.
6. The complainant replied asking for clarifications on the grounds for rejecting its tender as abnormally low. In reply, the Delegation explained that the evaluation committee had carefully considered the clarifications provided in light of the market conditions and nature of the requested service. It found that “the company may not be able to guarantee a suitable replacement if the expert included in the offer becomes unavailable or needs to be replaced which could impact the continuity of the service”.
7. The complainant, in reply to the Delegation, argued that the justification provided for rejecting the tender as abnormally low due to concerns over service continuity were not in line with the definition of an abnormally low tender as provided in Article 2.6.10.1 of the Practical Guide to contract award procedures for European Union external action (PRAG).[4] In particular, these concerns did not relate to the price or to the sustainability of the offer.
8. In October 2025, the Delegation explained that the evaluation committee considered that the clarifications provided by the complainant had not adequately addressed the doubts expressed as they lacked sufficient detail and supporting documentation or evidence.
9. The complainant contacted the Commission about the matter. The Commission explained that only the specific contracting authority, in this case the Delegation, could address his concerns over the evaluation and that there was no mechanism for review by the Commission.
10. Dissatisfied with the replies received, the complainant turned to the Ombudsman in October 2025.
The inquiry
11. The Ombudsman opened an inquiry into the Delegation’s decision to reject the complainant’s tender as abnormally low. In particular, she asked for clarifications on the grounds for rejecting the tender and asked to inspect all documents concerning this call for tender.
12. In the course of the inquiry, the Ombudsman’s inquiry team inspected the Delegation’s file on the case. The Commission, acting as the framework contracting authority, provided a written reply on the complaint. The reply was shared with the complainant, who provided comments.
Arguments presented to the Ombudsman
By the Commission
13. The Commission explained that, when evaluating the offers received, the evaluation committee found that the price offered by the complainant was significantly lower than that of other tenderers, which raised suspicions of the tender being abnormally low. It thus followed the procedure set out in the Financial Regulation[5] and the PRAG,[6] and asked the complainant for clarification on the applicable social, labour law and security obligations, backstopping services and information on business continuity in the event the expert became unavailable. The evaluation committee did not request the complainant to provide a specific list of supporting documents but left it at its discretion to determine how to demonstrate that the price was justified. The Commission noted that the complainant had not requested any further clarification in this regard.
14. In reply to that request, the Commission noted that the complainant had provided generic explanations, with no supporting evidence, and had merely stated that the price offered was compliant with local market conditions, mentioning past experiences in Papua New Guinea. The complainant had failed to specifically address the low fees quoted, in particular the management fee, which was significantly lower than that of other tenderers. The Commission noted that it was unrealistic to propose such a low management fee to carry out all the tasks listed in the global terms of reference and in the complainant’s offer, which also included backstopping activities. This raised serious doubts over the feasibility of the tender at the price proposed, including considerations over business continuity in case of replacement of the expert. The evaluation committee thus rejected the complainant’s tender as abnormally low.[7]
15. The Commission noted that, following the award decision, the service contract was signed ‘urgently’ due to pressure from the national authorities in Papua New Guinea to have the technical expertise in place as soon as possible. The Commission further clarified that, in the subsequent exchanges with the complainant, the Delegation could not disclose information on the prices offered by other tenderers to protect their commercial interests. The information disclosed by the Delegation to the complainant was thus limited, focusing on business continuity aspects, including backstopping. The Commission noted that, regrettably, this information was interpreted as inconsistent rather than complementary. The Commission nevertheless clarified that the Delegation’s rationale for rejecting the complainant’s tender was the exceedingly low price quoted which could jeopardise the provision of services.
16. The Commission stated that, following receipt of the complaint to the Ombudsman, the Delegation had reassessed the matter and maintained its conclusion that the complainant’s offer was abnormally low. It provided this assessment to the Ombudsman in a confidential annex to its reply.
By the complainant
17. The complainant claimed that, when requesting clarifications, the evaluation committee failed to identify specific concerns regarding the price offered, including concerns relating to the expert and management fees. The evaluation committee also failed to specify which documents the complainant should have provided to substantiate the price offered. This prevented the complainant from providing more specific clarifications and better addressing the committee’s concerns.
18. The complainant further claimed that the decision of the Delegation to reject its tender as abnormally low was not sufficiently reasoned. In particular, the Delegation had failed to explain why the complainant’s clarifications were considered insufficient, or to identify the specific concerns underlying its decision.
19. The complainant claimed that, while the Commission provided detailed arguments in its reply to the Ombudsman, such explanations were not communicated to the complainant during the procurement procedure. It stated that explanations produced after the completion of the evaluation procedure cannot remedy an initial insufficient statement of reasons. Moreover, it noted that considerations over the urgency of the procedure cannot justify the Delegation’s failure to adequately reason its decision.
20. On the assessment provided by the Commission, the complainant claimed it relied too much on a comparison with other offers and benchmark values. It claimed that the fact that the price of a tender is below a reference ceiling does not prove that it is abnormally low. Rather, the complainant claimed it had explained that the low price was justified by the hiring of a local expert and existing management and administrative structures across multiple assignments. In addition, the complainant found it hard to reconcile the strong technical evaluation of the backstopping arrangements proposed with the conclusion that the financial offer made the sustainability of the backstopping unrealistic.
21. The complainant noted that its tender ranked among the strongest technical offers. The rejection of its tender as abnormally low meant that its financial offer was not evaluated. This resulted in the potential loss of a contract for the complainant, which has a considerable financial impact. The complainant asked the Ombudsman to consider requesting compensation or a friendly solution from the Commission.
The Ombudsman's assessment
22. The Financial Regulation provides that a tender is irregular when the contracting authority declares it to be abnormally low.[8] The concept of abnormally low tenders refers to situations where the price of the tender of an economic operator raises doubts as to whether the tender is economically sustainable and compliant with applicable legal obligations and whether it can be performed in accordance with the requirements of the tender.[9]
23. The Financial Regulation does not clearly define what an abnormally low tender is. It merely states that, when a tender appears to be abnormally low, the contracting authority shall request in writing details from the tenderer and give it the opportunity to present its observations.[10] The Financial Regulation nevertheless provides some guidance as to the elements to be taken into consideration by the contracting authority when making this assessment.[11] It also mentions that the contracting authority shall reject a tender when it “does not comply with applicable obligations in the fields of environmental, social and labour law”.[12] If the evidence supplied does not satisfactorily account for the low price or costs proposed, the contracting authority should then reject a tender as abnormally low.[13]
24. In the absence of a clear definition, it is for the contracting authority to determine the method used to identify abnormally low tenders, provided that this method is objective and not discriminatory. The EU institutions have developed their own internal guidance to assist contracting authorities in this assessment.[14]
25. Therefore, the contracting authority enjoys a degree of discretion in determining if a tender is abnormally low. It is not for the Ombudsman to take a decision on whether the tender was abnormally low or not, as that decision is ultimately a decision of the contracting authority. The Ombudsman’s role in such cases is to assess whether the contracting authority carried out the procedure in accordance with the applicable rules, provided adequate reasons for its decision and did not commit a manifest error of assessment.
26. In this case, the Ombudsman notes that the Delegation did follow the two‑stage assessment procedure, in line with the Financial Regulation. Having first identified the tender as potentially abnormally low, the Delegation initiated the second stage of the procedure and sent a request for clarifications to the complainant. The Ombudsman finds that, on the basis of the inspected documents, this request was in line with the applicable rules, as the complainant’s tender did raise suspicions of being potentially abnormally low due to it being significantly lower than others.
27. The Ombudsman notes that, when requesting clarifications, the Delegation did not identify specific concerns regarding the price offered. It asked, in general terms, for clarifications on the low price proposed, including compliance with certain legal obligations, and questions on the backstopping services and business continuity. The Ombudsman finds that, given the legal consequences of this procedure, it would have been good administrative practice for the contracting authority to clearly identify the specific elements giving rise to the suspicion that the tender was abnormally low and indicate what evidence or information the complainant was expected to provide to address those concerns.
28. Regarding the concerns on business continuity in case of unavailability of the expert, the Ombudsman finds that this matter alone is not a component of the price and the failure to have a suitable replacement is not, in itself, evidence that the price quoted is abnormally low. The Delegation and the Commission failed to clarify how this matter was linked to the assessment of the tender’s financial feasibility. The Ombudsman finds that, if a matter is taken into consideration in assessing whether a tender is abnormally low, the contracting authority should be able to clearly explain its relevance to the assessment of the price quoted in the tender.
29. The Delegation then rejected the complainant’s tender as abnormally low because the complainant’s price was “considerably less than that of the normal market price, which may affect the sustainability of the service provision”. The Commission explained that this was the rationale for the rejection of the tender. The Ombudsman notes that this corresponds to the information in the documents inspected, in particular the ground for rejection provided in the evaluation report.
30. Nevertheless, the Ombudsman is of the opinion that the Delegation failed to sufficiently substantiate its decision, in breach of the duty to state reason.[15] In particular, the Commission’s own guidance on abnormally low tenders provides that assessments of abnormally low tenders should be properly documented and substantiated in the evaluation report, and that replies should be provided to any related requests or questions. Moreover, the PRAG provides that, following the rejection of a tender as abnormally low, the statement of reasons needs to include sufficient details to allow the unsuccessful tenderer to understand how the contracting authority reached its conclusion and allow it to challenge the decision.[16] While a tender being below the normal market price is a sufficient reason to contact the complainant and request clarification, it cannot be, in itself, a sufficient explanation for the rejection of the tender as abnormally low.
31. Based on the inspection of the case file, the Ombudsman found that neither the evaluation report nor any other document in the file contained details of the evaluation committee’s or the Delegation’s substantive assessment on the abnormally low nature of the tender or explained how the evaluation committee had reached this conclusion. The evaluation report merely stated the ground for rejection, without explaining what was meant by the “normal market price”, which specific component of the price gave rise to doubts over their feasibility, or on what basis the price was considered unsustainable. The further clarification provided by the Delegation, while considered ‘complementary’ by the Commission, relied on elements which were, as noted above, not clearly linked to the price and should not have been taken into account, as such, in the context of the procedure to determine the abnormally low nature of the tender. The Delegation also mentioned that the complainant’s clarifications lacked sufficient details and supporting evidence, without explaining why it considered this to be the case.
32. The Ombudsman finds that a decision rejecting a tender as abnormally low has a significant impact on a tenderer and should be duly substantiated and documented, in line with the Commission’s own guidelines. This was not the case in this case.
33. In the course of this inquiry, the Commission did provide more detailed clarifications on the decision to reject the tender as abnormally low. In particular, it explained what component of the price raised specific doubts and why the complainant’s tender was considered abnormally low. Moreover, the Commission also stated that, in the course of the Ombudsman’s inquiry, the Delegation reassessed the matter and came to the same conclusion. It documented its assessment in a confidential internal note, providing a detailed explanation as to why the complainant’s tender was considered abnormally low.
34. The Ombudsman appreciates the clarification provided on the reasons for rejecting the complainant’s tender as abnormally low. While the Ombudsman notes that the price offered by the complainant was indeed substantially lower than that of other tenderers and that the complainant’s clarifications were limited, the Ombudsman recalls that the Delegation’s request for clarification to the complainant was general and did not raise with the complainant the issues then referred to by the Commission. Moreover, the Ombudsman finds that the clarifications provided by the Commission focused on a comparison of prices, without explaining why the specific clarifications provided by the complainant did not sufficiently address the concerns about the low price offered. As noted above, the fact that a tender is below the normal market price is not, in itself, a sufficient reason for rejecting it as abnormally low.
35. In light of the above, the Ombudsman considers that the way in which the Delegation dealt with the matter amounts to maladministration. In this case, the Ombudsman will not issue any recommendation, as the contract has been awarded and is being implemented by the successful tenderer, which has acquired rights under the contract. Moreover, it is for the Court of Justice of the EU to annul a decision rejecting a tender and to award damages to the tenderer for its loss of opportunity, if warranted. The Ombudsman will nevertheless make suggestions with a view to preventing a similar situation occurring in the future.
Conclusion
Based on the inquiry, the Ombudsman closes this case with the following finding:
The Delegation of the European Union to Papua New Guinea’s acted with maladministration in how it carried out the procedure to determine whether the tender was abnormally low.
Suggestions for improvement
The Commission should take action to ensure that EU Delegations’ staff dealing with public procurement procedures have sufficient guidance on how to carry out the assessment of whether a tender is abnormally low. In particular, the Commission should ensure that:
a) when asking a tenderer for clarification regarding a suspicion that its tender is abnormally low, the contracting authority clearly identifies the specific elements giving rise to that suspicion and indicates what evidence or information the tenderer is expected to provide to address those concerns;
b) where a matter is taken into consideration in assessing whether a tender is abnormally low, the contracting authority is able to clearly explain its relevance to the assessment of the tender prices;
c) in line with EU law on the duty to state reasons and the Commission’s own guidelines, decisions to reject a tender as abnormally low are duly substantiated and sufficient reasons are provided to the unsuccessful tenderers.
Teresa Anjinho
European Ombudsman
Strasbourg, 07/10/2026
[1] The Contracting Authority for FWC SEA 2023 is the European Commission.
[2] Backstopping services consist of technical, advisory, coordination and other support provided by the contractor to facilitate the implementation of an assignment.
[3] Regulation 2024/2509 on the financial rules applicable to the general budget of the Union (hereinafter “Financial Regulation”): https://eur-lex.europa.eu/eli/reg/2024/2509/oj/eng.
[4] Available here: https://international-partnerships.ec.europa.eu/funding-and-technical-assistance/guidelines/contract-award-procedures-european-union-external-action-practical-guide-prag_en.
[5] Annex 1, point 23 of the Financial Regulation.
[6] Section 3.4.4 of the PRAG.
[7] on the basis of section 3.4.4 of the PRAG and Annex 1, point 23.2 of the Financial Regulation.
[8] Financial Regulation, Annex I, point 12.2.(d).
[9] See PRAG section 2.6.10. ‘Abnormally low tenders and foreign subsidies’.
[10] Financial Regulation, Annex I, point 23.1.
[11] Financial Regulation, Annex I, point 23.1. (a) the economics of the manufacturing process, of the provision of services or of the construction method; (b) the technical solutions chosen or the exceptionally favourable conditions available to the tenderer; (c) the originality of the tender; (d) compliance of the tenderer with applicable obligations in the fields of environmental, social and labour law; (e) compliance of subcontractors with applicable obligations in the fields of environmental, social and labour law; (f) the possibility of the tenderer obtaining State aid in compliance with applicable rules.”
[12] Financial Regulation, Annex I, point 23.2.
[13] Financial Regulation, Annex I, point 23.2.
[14] See section 2.6.10.1 of the PRAG and Commission explanatory note on abnormally low tenders, October 2023 (internal).
[15] The duty to sate reason is enshrined in Article 41(2)(c) of the Charter of Fundamental Rights, Article 296 of the TFEU and Article 18 of the European Code of Good Administrative Behaviour: https://www.ombudsman.europa.eu/en/document/en/3510.
[16] PRAG section 2.6.10.1.