Decision on the time taken by the European Data Protection Supervisor (EDPS) to deal with two complaints (case 3454/2025/TM)

The case concerned the time taken by the European Data Protection Supervisor (EDPS) to decide on two complaints made by the same complainant in 2023 concerning the processing of the complainant’s personal data.

In the course of the Ombudsman’s inquiry, the EDPS provided reasonable explanations concerning the handling of the cases and the delay. The EDPS has also finalised its preliminary assessment of the issues raised.

The Ombudsman also noted that the EDPS took measures aimed at addressing its backlog to avoid similar situations in the future and therefore closed the case with the conclusion that no further inquiries were justified. 

Background to the complaint

1. The complainant is an EU staff member. In June 2023, they submitted two separate complaints to the European Data Protection Supervisor (EDPS) about the processing of their personal data by their employer, an EU Institution, Body, Office or Agency (IBOA) and other organisational and technical issues to ensure that personal data of staff members is processed in an appropriate manner.  

2. In June 2023, the EDPS decided to pursue one of the two complaints and asked the IBOA concerned to provide comments.

3. In July and September 2023, the complainant sent additional information as regards the second complaint. In November 2023, the EDPS decided to pursue the second complaint.

4. In October 2023 and in March 2024, regarding the two complaints in question, the complainant sent additional information and raised new allegations. The EDPS requested additional clarifications from the IBOA. 

5. In September 2025, the EDPS contacted the complainant, apologising for the delay in handling their two complaints, adding that both were being treated as a priority.

6. In October 2025, the complainant provided more information to the EDPS following a related judgment of the EU General Court. In November 2025, the complainant asked the EDPS for a timeline for finalising its assessment. The EDPS replied that it was assessing the judgment and that it was not yet in a position to provide the requested timeline. The EDPS reiterated that both cases were being dealt as a priority.

7. In December 2025, dissatisfied with how the EDPS handled the matter, the complainant turned to the Ombudsman.

The inquiry

8. The Ombudsman opened an inquiry into the time taken by the EDPS to decide on the complaints.

9. In the course of the inquiry, the Ombudsman received the EDPS’s reply on the complaint to the Ombudsman. The complainant was given the opportunity to comment on the EDPS’s reply. As the EDPS issued in the meantime its preliminary assessment[1] on the two cases, the complainant chose not to provide any further comments in the context of the Ombudsman’s inquiry.  

Arguments presented to the Ombudsman

10. The complainant considered that the EDPS took an excessively long time to deal with their complaints.

11. The EDPS recognised the importance of handling complaints diligently and within a reasonable time and acknowledged that the handling of the complaints took longer than would normally be the case. The EDPS apologised to the complainant for the delay. The EDPS said that, throughout the procedure, it strived to keep the complainant informed about the progress of the two cases.

12. In its reply to the Ombudsman, the EDPS provided a timeline of the investigation steps taken and argued that the delay was justified by the complexity of the cases, the evolving circumstances of the investigations, and the significant resource constraints it faced during the relevant period.

13. In particular, the EDPS explained that the complainant had submitted additional allegations and information at different stages of the procedure that significantly broadened the scope of the initial complaints. The EDPS thus needed time to assess the additional information and decide on the most appropriate next step. The EDPS further explained that, given the factual and legal links between the two complaints, it decided to assess them jointly to ensure the required degree of coherence and completeness.

14. The EDPS underlined that, during the period concerned, it faced resource constraints and a significant increase in its workload. It recognised though that human resource shortages cannot justify unreasonable delays in handling a complaint. To that end, the EDPS had put in place staff reinforcement and other internal organisational measures specifically aimed at streamlining the complaint handling and avoiding similar issues in the future.

15. During the inquiry, in February 2026, the EDPS adopted its preliminary view on both cases.[2]

The Ombudsman's assessment

16. It follows from the principles of good administration that EU bodies should take decisions within a reasonable time frame.[3] This is particularly so when the procedure concerns fundamental rights such as the rights to protection of personal data and privacy protection.[4]

17. What is a ‘reasonable time’ depends on the circumstances of the case. Factors to be taken into consideration are, amongst others, the complexity of the case, the conduct of the parties, the various procedural steps taken by the administration and the overall context of the case.[5] The requirement to act within a reasonable time does not only apply to the entire length of the procedure, but also to the time taken between each procedural step.[6] If the duration exceeds a reasonable time, it is for the administration to justify the delay[7] and to proactively inform the complainant about the progress of the case.[8]

18. In the course of the inquiry, the EDPS provided reasonable explanations to justify parts of the delay in assessing the complaints. In particular, the EDPS explained that the complainant submitted additional information that “broadened the factual and legal scope” of the initial complaints. It was thus reasonable that the EDPS needed time to assess this information and decide on the most appropriate follow-up. The Ombudsman also notes that it was reasonable for the EDPS to handle both complaints jointly, given their factual and legal links, to ensure a coherent and comprehensive approach and full compliance with the relevant data protection rules.

19.  That said, the Ombudsman notes that the EDPS took almost one year and a half to assess the additional information and arguments provided by the complainant and to decide on its next step (from March 2024 to September 2025). In its reply to the Ombudsman, the EDPS acknowledged that this delay was partly due to lack of resources.

20. The Ombudsman has previously held that IBOAs have an obligation to organise their services in a manner enabling them to fulfil their duties.[9] The Ombudsman is aware of the strains put on the EU administration in having to handle a rising number of tasks and complaints without a corresponding increase in human or material resources. In this regard, the Ombudsman welcomes the measures taken by the EDPS in 2025 aiming to address its backlog and to prevent similar issues in the future.

21. After careful consideration, the Ombudsman considers that, during the inquiry, the EDPS provided reasonable and convincing explanations to justify the time it took to assess the two cases in question. Considering also that the EDPS has now provided to the complainant a preliminary assessment of their two complaints, and in the absence of further comments by the complainant, the Ombudsman finds that no further inquiries are justified into the complaint.

Conclusion

Based on the inquiry, the Ombudsman closes this case with the following conclusion[10]:

Given that, during the inquiry, the European Data Protection Supervisor provided reasonable explanations to justify parts of the delay in the handling of the two complaints at issue and that it has taken measures aimed to address its backlog and avoid similar situations in the future, no further inquiries are justified.

The complainant and the European Data Protection Supervisor will be informed of this decision.

 

Teresa Anjinho

European Ombudsman

Strasbourg, 21/07/2026

 

 

[1] In line with Article 18 of the EDPS Rules of Procedure, available at: https://www.edps.europa.eu/about/office-edps/edps-rules-procedure_en.

[2] In line with Article 18 of the EDPS Rules of Procedure, available at: https://www.edps.europa.eu/about/office-edps/edps-rules-procedure_en.

[3] See for instance the Ombudsman’s decisions in case 1609/2021/VS, available at: https://www.ombudsman.europa.eu/en/decision/en/158433 and in case 2029/2020/PL, available at: https://www.ombudsman.europa.eu/en/decision/en/147845. See also Article 41 (1) of the Charter of the Fundamental Rights of the European Union, available at https://eur-lex.europa.eu/legal-content/EN/TXT/HTML/?uri=CELEX:12012P/TXT#d1e570-393-1.

[4] See for instance the Ombudsman’s decisions in case 1888/2023/TM, available at: https://www.ombudsman.europa.eu/en/decision/en/195224, and in case 1609/2021/VS, available at: https://www.ombudsman.europa.eu/en/decision/en/158433.

[5] See for instance judgment of the Court of Justice of 17 December 1998, Baustahlgewebe v Commission, case C-185/95 P, paragraph 29, available at: http://curia.europa.eu/juris/showPdf.jsf;jsessionid=8F1C0778C9B8C96192ACB213E890C455?text=&docid=43779&pageIndex=0&doclang=EN&mode=lst&dir=&occ=first&part=1&cid=4441718 and the Ombudsman’s decision in case 484/2015/DR, point 28, available at: https://www.ombudsman.europa.eu/en/decision/en/90382.

[6] See for instance the judgment of the Court of Justice of 2 June 1994, De Compte v Parliament, case C-326/91 P, paragraph 21, available at: http://curia.europa.eu/juris/showPdf.jsf?text=&docid=98282&pageIndex=0&doclang=EN&mode=lst&dir=&occ=first&part=1&cid=4442402 and the Ombudsman’s decision in case 1873/2018/LM, point 23, available at: https://www.ombudsman.europa.eu/en/decision/en/129250.

[7] See for instance the judgment of the Court of Justice of 5 May 1983, Ditterich v Commission, case 207/81, paragraph 26, available at: http://curia.europa.eu/juris/showPdf.jsf?text=&docid=91654&pageIndex=0&doclang=EN&mode=lst&dir=&occ=first&part=1&cid=4443230.

[8] See for instance the Ombudsman’s decisions in case 1888/2023/TM, available at: https://www.ombudsman.europa.eu/en/decision/en/195224 and in case 1873/2018/LM, available at: https://www.ombudsman.europa.eu/en/decision/en/129250.

[9] Ibid.

[10] This complaint has been dealt with under delegated case handling, in accordance with the Decision of the European Ombudsman adopting Implementing Provisions