Decision of the European Ombudsman on complaint 1574/2002/GG against the European Commission
Decision
Case 1574/2002/GG - Opened on Tuesday | 10 September 2002 - Decision on Thursday | 23 January 2003
Dear Mr C.,
On 1 September 2002, you made a complaint to the European Ombudsman against the European Commission. This complaint concerned a contract entered into by the Irish Sea Fisheries Board and the European Commission's DG XIV by which the Board undertook to carry out research into "The Physical Interaction between Grey Seals and Fishing Gear".
On 10 September 2002, I forwarded the complaint to the President of the European Commission.
On 14 September 2002, you sent me a further message in relation to your complaint which I forwarded to the Commission on 17 September 2002. You were informed accordingly in a letter sent the same day.
Further documents relating to your complaint were submitted by you under cover of a letter of 16 September 2002. I forwarded this letter and these documents to the Commission on 25 September 2002.
On 19 September 2002, you asked for advice in relation to a letter you proposed to send to the Irish authorities. In my reply of 23 September 2002 I explained that I was not in a position to give advice in such a case and suggested that you could contact the Irish ombudsman if problems should arise.
On 29 September 2002, you sent me a further query in relation to your complaint to which I answered on 2 October 2002.
The Commission sent its opinion on 17 October 2002. I forwarded it to you on 18 October 2002 with an invitation to make observations, which you sent on 22 October and 16 December 2002.
I am writing now to let you know the results of the inquiries that have been made.
THE COMPLAINT
The complainant, an Irish citizen, used to work for the Irish Sea Fisheries Board (an Irish authority). In 1993, the Board had entered into a contract (reference number PEM/93/06) with the European Commission's Directorate-General (DG) XIV (Fisheries) by which the Commission undertook to provide a maximum of 62 000 Ecu (47,7 % of the total cost) towards the cost of research into "The Physical Interaction between Grey Seals and Fishing Gear". The complainant was the responsible scientist on this research contract.
According to the complainant, a draft final report was submitted to the Commission in March 1997. The complainant alleged that the draft report had been written by himself to at least PhD standard and had been informally peer-reviewed before being sent to the Commission. In a letter dated 7 May 1997, the Commission informed the complainant that the draft report had been evaluated and had been "accepted as a satisfactory final report". According to the complainant, once this draft final report had been accepted by the Commission, it could not be changed in any significant way in the final report. In the complainant's view, the Board was obliged to publish the report as soon as possible after the draft version had been accepted.
According to Article 3 ("Reports and documents") of the contract, the tasks carried out by the contractor in performance of this contract were to be the subject of reports drawn up in accordance with Annex III. The latter detailed in particular how the final report had to be set out and specified that the draft (final) report had to be submitted to the Commission by a certain date. Annex III further stipulated: "The Commission will then either notify its acceptance to the Contractor or will send him its comments. Within one month of receiving any comments from the Commission, the Contractor will send the Commission the definitive report, which will either take account of these comments or will put forward alternative points of view. (.)"
Article 9 (2) of the General Terms and Conditions applicable to Contracts awarded by the Commission of the European Communities (Annex I) provided that copyright and other property rights in respect of "manuscripts" were to belong exclusively to the EU, unless such rights already existed. Article 9 (3) stipulated that all rights in manuscripts were to be acquired by the EU on the "date of acceptance".
The complainant alleged that after the draft final report had been accepted by the Commission, he was informed that the Board's parent civil service authority, the then Department of the Marine & Natural Resources, was very unhappy with the draft report and had demanded editorial control over the drafting of the final report. The complainant resigned from the Board in September 1997. He submitted that substantial changes had subsequently been made to the draft final report and that the final report that was published more than a year after he had left bore little resemblance to the draft version. In the complainant's view, the final report negated, neutralised or deleted the main findings of the main report.
In an article in the journal "Fishing News" published in October 2000 (a copy of which was submitted to the Ombudsman), the complainant alleged that the main difference between the two reports was that the description of an experiment set out in the draft final report was missing in the final report. According to the article, this experiment showed that seals were able to remove whole fish from gillnets. The complainant argued that the removal of the experiment permitted the final report to describe the loss of fish that had been noted as "possibly having been caused by conger eels or other large predators".
On 8 May 2002, the complainant submitted a complaint to the Ombudsman (complaint 836/2002/GG). This complaint was rejected by decision of 27 May 2002 on the grounds that the complainant had not yet made the appropriate prior approaches to the Commission.
The complainant then wrote to the Director-General of DG Fisheries at the European Commission on 13 June 2002 asking for explanations as to why the Commission had allowed the draft final report to be changed. According to the complainant, neither a reply nor an acknowledgement of receipt had been received by him by the time he decided to renew his complaint to the Ombudsman in September 2002.
In his new complaint, the complainant in substance alleged (1) that the Commission had failed to comply with the rules in force when it allowed the Board to make substantial changes to the report as compared to the draft report that had been accepted by it and (2) that the Commission failed to reply to his letter of 13 June 2002 asking for an explanation as to why these changes had been allowed.
THE INQUIRY
The Commission's opinionIn its opinion, the Commission made the following comments:
Much of the complaint appeared to address itself to matters internal to the Board and the Department rather than to matters relating to the Commission.
The complainant argued that the draft final report could not be changed in a significant way once it had been accepted by the Commission. In so far as contractual aspects were concerned, perusal of the contract and its annexes did not reveal any such requirement. As regarded procedural aspects, it was not common but it was not unknown for a final report to differ from a draft final report, although the latter had been accepted by the Commission. It was, after all, the responsibility and duty of the contractor (i.e., the Board) to deliver the final report in the form it saw as appropriate. The Commission did not wish to intervene in such a process.
The Commission's main parameter leading to acceptance or rejection of a report, be it draft or final, was whether the terms of the contract had been observed. This had been the case for this contract. Wherever the Commission saw deficiencies in the scientific analysis of the results of the work carried out during the contract, appropriate comment would be made to and modification requested from the contractor. However, this had not been the case for this contract either in the draft report or in the final report. If the contractor wished to alter conclusions resulting from the scientific analysis in its final report, it should be and was entitled to do so.
The contract originally required the Board to provide a cost statement, and hence finalise the contract, by 15 January 1998. However, the Commission had been contacted by fax on 7 January 1998 by the Board that had explained that the complainant had left without preparing a cost statement. The Board had therefore requested an extension until mid February 1998. In addition, the Board had requested an extension of the contract until the middle of June 1998 to allow time to make changes to the final report. The Commission had, by letter of 9 January 1998, agreed to this request.
The complainant's observationsIn his observations, the complainant stressed that the changes made to the draft final report had rendered the latter obsolete and that the changes did not only affect the conclusions but that important sections on the scientific data and analyses had been removed.
The complainant added that if the Commission was entitled to accept the changes between the two reports, a considerable amount of taxpayer's money had been wasted.
THE DECISION
1 Preliminary remark1.1 The present complaint concerns a contract (reference number PEM/93/06) between the Irish Sea Fisheries Board (an Irish authority) and the European Commission's Directorate-General (DG) XIV (Fisheries) by which the Commission undertook to provide part of the cost of research into "The Physical Interaction between Grey Seals and Fishing Gear". The complainant, who was working for the Board at the time and who was the responsible scientist on this research contract, alleges that the draft final report was substantially changed due to the interference of another Irish authority, the then Department of the Marine & Natural Resources, after it had been accepted by the Commission.
1.2 The Commission argues that much of the complaint concerns matters internal to the Board and the said Department. The complaint itself, however, is directed at the Commission, and the present decision only deals with the allegations against the European Commission.
1.3 In his observations, the complainant argues that the Commission's approach resulted in a considerable waste of taxpayer's money. In the absence of any supporting evidence, the Ombudsman is not in a position to ascertain whether this further allegation is well-founded. The complainant could however consider informing the European Court of Auditors (12, rue Alcide De Gasperi, L-1615 Luxembourg) that would be able to look into the matter.
2 The Commission's acceptance of substantial changes to the draft final report2.1 The complainant alleges that the Commission failed to comply with the rules in force when it allowed the Board to make substantial changes to the report as compared to the draft report that had been accepted by it.
2.2 The Commission takes the view that it is the contractor's responsibility to deliver the final report in the form which it considers appropriate and that the Commission does not wish to intervene in such a process. According to the Commission, perusal of the contract did not reveal a requirement such as the one alleged by the complainant.
2.3 The Ombudsman notes that the Commission does not dispute the complainant's allegation that substantial changes were made to the draft final report that the Commission had accepted. He considers, however, that the Commission's view according to which it was the responsibility and duty of the contractor to deliver the final report in the form it saw as appropriate appears to be reasonable.
2.4 In these circumstances, there appears to be no maladministration on the part of the Commission in so far as the first allegation is concerned.
3 Failure to reply to letter of 13 June 20023.1 The complainant alleges that the Commission failed to reply to his letter of 13 June 2002 asking for an explanation as to why the Commission had allowed these changes to be made.
3.2 In its opinion, the Commission has failed to address this allegation. It has however provided a reply to the question raised by the complainant in the said letter in its opinion.
3.3 It is good administrative practice to reply to letters from citizens within a reasonable time-limit(1). According to the Commission's own Code of good administrative behaviour, a reply to a letter addressed to the Commission shall be sent within fifteen working days from the date of receipt(2). In the present case, the Commission only addressed the question raised by the complainant in a letter of 13 June 2002 in its opinion that was submitted to the Ombudsman on 17 October 2002. The Commission's failure to reply to the complainant's letter within an appropriate period thus constitutes maladministration. A critical remark will be made in this regard.
4 ConclusionOn the basis of the Ombudsman's inquiries into this complaint, it is necessary to make the following critical remark:
It is good administrative practice to reply to letters from citizens within a reasonable time-limit(3). According to the Commission's own Code of good administrative behaviour, a reply to a letter addressed to the Commission shall be sent within fifteen working days from the date of receipt(4). In the present case, the Commission only addressed the question raised by the complainant in a letter of 13 June 2002 in its opinion that was submitted to the Ombudsman on 17 October 2002. The Commission's failure to reply to the complainant's letter of 13 June 2002 thus constitutes maladministration.
Given that these aspects of the case concern procedures relating to specific events in the past, it is not appropriate to pursue a friendly settlement of the matter. The Ombudsman therefore closes the case.
The President of the Commission will also be informed of this decision.
Yours sincerely,
Jacob SÖDERMAN
(1) Cf. Article 17 (1) of the European Code of Good Administrative Behaviour proposed by the Ombudsman and approved by the European Parliament (available on the Ombudsman's website: http://www.ombudsman.europa.eu).
(2) Published in OJ 2000 no. 267 page 63 (sub 4).
(3) Cf. Article 17 (1) of the European Code of Good Administrative Behaviour proposed by the Ombudsman and approved by the European Parliament (available on the Ombudsman's website: http://www.ombudsman.europa.eu).
(4) Published in OJ 2000 no. 267 page 63 (sub 4).