Termination of Grant Agreement
Case 17/2012/PMC - Opened on Monday | 27 February 2012 - Decision on Monday | 18 May 2015 - Institution concerned European Commission ( Friendly solution )
Allegation(s)
1) The European Commission unlawfully and/or unfairly terminated Grant Contract ENPI/2009/203-997 and in particular failed to give reasons for its decision.
2) The Commission failed to manage the Project with due diligence.
Claim(s)
1) The Commission should reconsider the decision to terminate Grant Contract ENPI/2009/203-997.
2) The Commission should approve the amendment to the Grant Contract and authorize the participation in the project of the new Armenian partners (University of Yerevan and Armvir Region).
3) The Commission should release the second instalment of the grant.
4) The Commission should transfer the management of the Project from the EU Delegation in Armenia to the EU Delegation in Jordan.